Huge DC in loading bay fitout September 1st 2011 Easilift has completed a £6.5 million loading bay installation for Tesco's Daventry DC
Easilift Loading Systems completed what is said to be largest
single order ever placed in the UK for loading bay
equipment. The bespoke solution for Tesco's new state-ofthe-
art Grocery Distribution Centre in Daventry saw Easilift
successfully deliver a project worth in excess of £6.5 million. The
800,000 sq ft facility is a major investment designed to meet
Tesco's long-term distribution requirements.
Working closely with
Tesco and the main
contractor Volker
Fitzpatrick, Easilift project
managed the installation of
40 double deck lifting
platforms and 100 dock
leveller bays, all housed in
external loading pods.
"Easilift has proven its
abilities in the past, and we
knew that by involving them
in the process from the
start, we could maximise
resources to deliver a robust
loading bay environment on
a scale never attempted before in UK distribution," explains
Duncan Robertson, project manager at Tesco.
The design interface was critical to the success of the project
and Easilift worked closely with the project team to overcome a
number of technical challenges. Restrictions at yard level meant
that the double deck bays had to be constructed in pairs. This
innovative arrangement created a tandem pod around a single
walkway to ensure safe and easy operator access.
Each of the 40 double deck bays incorporates a heavy duty,
surface mounted 16,000kg lifting platform, capable of carrying
up to 30 roll cages. The lifts are located within external modular
pods, manufactured and partially preassembled at Easilift's
Huddersfield factory prior to delivery and final on-site erection
using a 60-tonne crane. This approach equated to a 60%
reduction in installation time for this particular element, when
compared with previous
lift installations. The dock
leveller bays comprised
96 type 232 PoweRamp
hinged lip units and 4
type PoweRamp
telescopic lip units with
each bay comprising a
modular loading pod, a
type 403 PowerShelter
and a 601 Powerdoor.
Ancillary equipment
included LED traffic and
loading dock lighting,
pod lights, fully
integrated control panels
and heavy duty slider bumpers.
Bays were fitted with a dock management system. This
innovative hi-tech management reporting and safety system is
designed to prevent the premature departure of vehicles from the
loading bay. The system combines Easilift's dock door and
associated control equipment with Traka's electronic key control
system and prevents vehicle
drive-off. More articles from Easilift Loading Systems Ltd: |