Loading bay equipment on demand February 1st 2008 Hörmann UK has
supplied and installed the
loading bay equipment at
the newly opened IKEA
store at Holywood
Exchange, Belfast.
The site is a massive
29,000m2 and the
construction of the project
was managed by pcm
management, which has
overseen various projects
for IKEA across the UK.
The specification was
for six specially angled 30º
pedestals and loading
houses which provide
access to manually
operated SPU40 doors.
Angled pedestals were
specified for this project as
they provide a wider
range for manoeuvring in
a limited turning area.
The pedestals, which
are galvanised in an
immersion bath, were
installed complete with
cladded loading houses
fitted in front of the
building and this design
affords maximum
warehouse space on the
inside of the loading bay. More articles from Hormann UK Ltd: |