Fast-track mezzanine service April 1st 2005 Welconstruct Customer Solutions has completed a fast-track contract to optimise space for automotive supplier, Calsonic Kansei, following a reorganisation of its manufacturing bases in the North East.
Calsonic required an existing mezzanine floor to be extended to house production facilities for heating ventilation/air conditioning units and instrument panels transferred from its Shildon site in County Durham.
Welconstruct designed and installed the required 100m2 extension, with a one hour fire rating, in just one month.
Calsonic engineering manager John Dixon said: “A quick conclusion to the project enabled us to continue service delivery without disruption.” More articles from Welconstruct: |