4-ways scale up further May 1st 2010 Heavy new truck from Combilift can
carry 25 tonne capacities and proves its
worth in modular server room facility
Combilift has launched its largest 4-way forklift, the 25
tonne capacity C25000.With dimensions of around
5x5m, an unladen weight of 32t and a 127kW engine, the
truck has been designed in response to developments in heavy
industries with companies looking for safer and more efficient
methods of handling larger loads.
The C25000 resembles a standard Combilift but on a much
larger scale. The manufacturer says the implications of designing
and building a truck almost twice as large as any existing model
called for some innovative engineering and manufacturing
solutions.
The Kubota engines used as standard in the diesel powered
Combilift range did not offer the required HP for a model of this
size, and after a thorough analysis of the market Combilift opted
for a John Deere engine. "We chose the John Deere 6068 HF not
only because of its 170 HP capacity but also because we found it
to be the quietest and most environmentally friendly option,"
says md Martin McVicar.
A critical issue was also the platform height. The size of three
single wheels required for a machine of this weight would have
resulted in an unworkable platform height, but by using double
wheels the platform has been kept to 1150mm. Hydraulic fork
positioners have also been incorporated as a standard feature,
much to the relief of drivers for whom it would be nigh on
impossible to shift the extremely heavy forks manually. The
shotblasting facility at the Monaghan assembly plant factory was
not large enough to cope with assembled parts so steel elements
were treated in sections before being assembled.
"We were definitely faced with some issues when we embarked
on this project," adds McVicar. "But our engineers once again
rose to the challenge to create a Combilift which will do the job
perfectly for the customer and which is remarkably
manoeuvrable considering its size."
Blade room project
Modular building firm BladeRoom is taking delivery of a C25000
model. Bladeroom produces energy efficient data centres and
needs a sound handling system at its new production facility in
Cinderford, Gloucestershire.
Having looked at a number of conventional handling vehicles
on the market, it became apparent that they were not going to be
up to the challenge of easily and quickly manouevering the
14x4.2m finished modules in and around the site.
BladeRoom's materials handling consultants HFT Forklifts
(Hereford) investigated various possibilities including overhead
gantry cranes and very large counterbalance trucks. The cranes
proved to be too inflexible, not practical to install in an L shaped
building and extremely expensive. The sheer physical size of a
counterbalance forklift capable of moving loads of 18t at
extended load centres would have taken up far too much space in
the manufacturing area.
"Materials handling is a crucial part of the build process" says
BladeRoom CEO Paul Rogers. "With the help of Kevin Heath at
HFT we realised that one possibility was a much larger version of
the 12t and 14t capacity Combilifts that we were already using.
These have been invaluable for moving raw materials such as
14m long RSJ's and for lifting assembled roof units onto base
units, so it seemed sensible to also look at a 4-way customised
approach to handle the finished modules."
Together with Combilift's official distributor in the West
Midlands Abex, and Combilift design engineers at the factory in
Monaghan, specifications were drawn up for the super sized
C25000 model. Its capacity will allow BladeRoom to easily lift the
fully fitted modules into place for pre delivery testing.
"The ideal solution from our point of view was a machine that
could move modules in the same way as other operations move
pallets – just on a much larger scale of course" adds Rogers.
In spite of the truck's size – it measures 5m by 5m, with a
3.2m high cab, its exceptional manoeuvrability will enable
BladeRoom to lay out the manufacturing area more efficiently.
Modules will be placed in rows to allow the Combilift to travel
sideways along gangways between them, and the 4m lift height
will enable modules to be doubled stacked.
BladeRoom's quality modular data centres can be supplied in
18 or 20 weeks compared to the equivalent in months for the
construction of traditional structures. The Combilift's flexibility
to "go anywhere and do anything" as Rogers puts it, will enable
the company to proceed at the required pace to fulfil orders on
the books as well as to cope with the growth it expects due to
more and more interest from
major firms around the world. More articles from Combilift Limited: |