High powered partnership February 1st 2009 EnerSys and Linde are keeping costs down, batteries optimised and utilisation high while
improving safety at logistics firms such as Culina and Norbert Dentressangle
When we looked at plans for
Haverhill we wanted something
different," says Jim Seymour,
Warehouse Manager at Culina, Haverhill.
"EnerSys worked with the truck supplier to
deliver a solution to remove manual handling
from battery changing and a management
system that takes all the guess work away
during charging. Looking at whole life cost
benefits we believe the new system will save
money over the five years of the contract."
Culina has four chilled and five ambient
distribution centres, with 1300 employees and
250 trailer units. The Haverhill development
opened on schedule in August 2008 and
covers 191,000 sq ft housing 17,500 pallets
along conventional wide aisle high bay racking
in a controlled 0-5C environment.
Culina expects that around 80 per cent of
the picking will be by the case once the
warehouse is fully operational and that it will
be shipping up to 1.5 million cases a week.
This makes the choice of warehouse trucks
vital to the operation. Linde and EnerSys had
previously supplied Prime Point. Culina asked
them to submit joint proposals for the new
site while participating in a competitive
tender. The requirement was for 15 reach
trucks for high bay and general pallet
handling and 70 other warehouse trucks to
support low level picking and general tasks.
Despite the advanced operations at its
existing facilities this was the first major
distribution centre fully commissioned by
Culina for its own requirements. The
company was able to use its experience at
Prime Point in particular to identify
enhancements to the way it manages
warehouse truck batteries.
One of Culina's requirements was to make
battery operations efficient and safe by
simplifying the change process and
minimising the amount of manual handling
required. EnerSys devised a layout with the
three different types of batteries in separate
zones. Batteries for low level order pickers
and powered pallet transporters are charged
at opposite ends of a single aisle. Reach
truck batteries are charged alongside a
second aisle that runs parallel to the first.
When one of the small trucks requires a
battery change it enters the area
and draws alongside the
designated charging
position. A simple
rail-guided trolley is
then positioned
between the truck
and the fully
charged battery.
The depleted
battery is
disconnected from
the truck and rolled
onto the trolley
platform and into the free
charging position. The replacement battery
is rolled out of its charging position and onto
the trolley which is then repositioned before
the unit is rolled onto the truck. The whole
process takes just a few seconds and is
completed without any lifting because the
platforms on the truck, trolley and charging
position are all at the same level. A simple
one-way system eliminates congestion
during busy periods and promotes safety.
A different operation is utilised for
changing the larger, heavier reach truck
batteries. Deciding powered puller
changeover would take too long, the
company specified a modified mobile
powered pallet transporter to bring the
batteries to the reach trucks parked adjacent
to the chargers. The trucks do not need to
enter the charging area or align themselves
with specialist handling equipment which
means the transfers are faster and more
efficient for improved overall productivity.
Another priority was to optimise overall
battery performance. This has been achieved
by a computerised management system that
works in conjunction with the intelligent
diagnostic capabilities of the batteries to
oversee every aspect of their utilisation.
Batteries are allocated in strict rotation which
means that the best available unit, the one
with the most charge, is always used.
Battery utilisation is spread more evenly so
that none gets heavier usage than the
others. The service life of the batteries is
prolonged and the risk of unexpected
maintenance issues is reduced.
EnerSys supplied its high-performance
Perfect Plus batteries which deliver extended
work cycles between charges. Charging is
achieved by Hawker LifeTech high frequency
chargers, with which energy efficiency is as
much as 20 per cent higher than
traditional 50 Hz chargers.
The charger automatically
detects the battery's level
of discharge and will
supply only the amount of
power needed and no
more to restore full
charge. Electrolyte levels
are correctly maintained
by the Aquafill system
using deionised water
manufactured by Culina at
Prime Point.
A large display mounted above the
charging area indicates where the correct
battery, the one with the most charge, can
be found. The combination of lift truck,
batteries and efficient management ensures
that changes are required just once every
shift on average.
"The management system should help to
ensure the batteries run for the full term,"
says Jim Seymour. "It reduces opportunity
charging and the risk of random selection.
It's so simple it does the work for the guys."
Collaboration at Dentressangle
EnerSys and Linde also recently collaborated
to optimise power source utilisation and
performance for 3PL, Norbert
Dentressangle. With its 'Power for Life'
service Enersys is able to monitor and
manage batteries to ensure the electric lift
trucks supplied by Linde continue to support
Norbert Dentressangle's ongoing operations
in the UK with the same levels of
performance, efficiency and value for
money over the entire length of a five year
contract at each warehouse.
Power for Life is designed to match
handling operations to battery resources so
that they work as close as possible to their
design parameters. Although experience
and planning enable Enersys and Linde to
predict the likely utilisation patterns very
well, it is important to monitor operations
during the first year in particular to optimise
performance and reduce the risk of
problems later in the contract. More articles from Enersys Ltd: |