Some bright sparks January 1st 2012 John Lewis Partnership has introduced novel battery
management from Enersys to control the energy used
by its warehouse truck fleet at Magna Park
The installation automatically
manages battery allocation to
ensure balanced utilisation,
minimises energy consumption and
prevents battery systems from drawing
too much power when overall demand in
the warehouse is above predetermined
limits. This ensures other services are not
disrupted and avoids the need for costly
additional electrical infrastructure to
keep the installation within budget.
The John Lewis Magna Park
distribution centre covers around 800,000
sq ft with 50 warehouse trucks on site,
including very narrow aisle combination
pallet stacker/order pickers, reach trucks,
ride-on pallet transporters, pedestrian
powered pallet trucks, and electric
counterbalance trucks.
One of the key considerations was the
provision of change and charge facilities
for the warehouse trucks. The warehouse
works hard over extended shifts and the
batteries need to support long intervals of
up to eight hours between charging. The
project team specified the highest capacity
batteries available for the various
warehouse trucks to help meet this
objective. The traditional approach for an
intensive operation like this is to select a
spare battery for each truck so that one
can be charged while the other is being
used. In practice the number of spare
batteries needed will depend on factors
such as the recharge time and the
frequency and number of changes.
Utilisation patterns at Magna Park
predicted a 60 per cent spare battery
capacity, in other words six spares for
every ten trucks. The reduction in battery
requirement has considerable benefits
including lower capital costs and reduced
space for the charging facilities.
Another consideration was the amount
of power consumed. The electrical
infrastructure for the building was
finalised early in the design process and,
while provision to the charging area was
more than adequate, subsequent changes
to meet evolving requirements of the
operation meant that additional power
supplies would be required. One estimate
put the cost of providing this additional
power supply to the charging area at
around Ł100,000. Instead the project team
looked at ways of limiting the amount of
power consumed by the battery chargers
without compromising the ability to
maintain warehouse truck availability.
EnerSys recommended a novel
implementation of its PowerNet battery
and power management system to oversee
all charging and changing operations. A
typical PowerNet installation allows
operators to manage their charging
patterns to take advantage of off-peak
rates for lower price electricity. However,
as the system runs on a standard PC and is
completely configurable in software, it can
be set up with a wide range of userdefined
parameters to provide a unique set
of performance characteristics.
"We decided to manage our power
requirements with PowerNet rather than
with a costly upgrade to the infrastructure,"
says Ted Weager, operations manager
MHE for the John Lewis Partnership.
Smart topping up
Under normal operations all of the
chargers can draw the power they need to
top up the battery to which they are
connected. However, if the available power
is low the system automatically shuts
down the chargers supplying the batteries
requiring the greatest amount of charge.
Power is then allocated to the remaining
batteries to ensure they are fully charged as
soon as possible and ready when a truck
requires a change. Batteries are brought
back online for charging whenever power
is available.
The batteries are charged with EnerSys
Powertech HF chargers. They
automatically detect the battery's level of
discharge and will supply only the amount
of power needed to restore full charge.
"The HF chargers are smaller and have
a premium price but they save on
electricity which helps us meet our
sustainability goals," says Weager.
The 'intelligent' diagnostic software in
the chargers transmits data via the system's
PC to a large display screen installed in the
changing area. The display clearly indicates
the order in which batteries should be
retrieved for each type of truck, ensuring
only fully-charged units are taken. The
system makes certain that all batteries
receive the correct amount of charge before
being used and that they are systematically
rotated, overcoming the potential problem
of operators simply taking the nearest
available battery, regardless of its true state
of charge. There is no longer any need to
dedicate batteries to specific trucks.
The reach truck and pallet transporter
batteries are arranged along one side of the
facility on roller beds with the chargers
mounted above for easy access and
identification. Batteries are changed using
an EnerSys Pro Series Tugger mounted on
a modified powered pallet transporter.
When a truck enters the changing room
the Tugger moves alongside and pulls the
battery onto its own platform using a
magnetic arm. The battery is taken to a
free charging position and a fully charged
unit, as indicated by the management
system, is transferred to the awaiting truck.
"The operation is quick, efficient and
requires no manual handling on the part
of the operator," says Ted Weager.
Alongside the main battery bank is a
smaller installation with one spare battery
for the six VNA combination trucks.
These are normally charged using an inaisle
system to minimise truck movements
and reduce the time spent off-duty. The
spare battery is used for periodic rotation
to ensure balanced utilisation and as
emergency back up.
"We wanted a system that provides us
with data that we can use to monitor
performance and make decisions about
future requirements," concludes Weager. More articles from Enersys Ltd: |